Today the Third & Bond bloggers from Hudson Companies explain the importance of everyone working well together...It isn’t about cooperation so much as coordination. At the site now we have six to seven trades working simultaneously. Each trade is focused solely on getting its own work done. To be efficient, they need to stay out of each other’s way and not fall behind. There’s a practical sequence for constructing a building that enables one trade to follow another. It starts with the obvious: excavation, then foundation, and then superstructure. Once the superstructure is in place, the trades must be coordinated with more forethought. The carpenter is first and comes through to lay out the track for the demising walls.